Vai al contenuto

LRT Precotto-M1-Gobba M2

Testi-Bicocca-Precotto LRT second part

Work in progress

  • Feasibility study not completed
  • Initial design completed
  • Final design not completed
  • Executive design not completed
  • Works management not completed

Stops: 5

Length of the line: 1.5 km (0.9 miles)

This is the eastward completion of the Testi - Bicocca - Precotto LRT and as such has the same characteristics. At a tangent, it crosses the north-east quadrant of the municipality of Milan, which is also affected by a simultaneous redevelopment resulting from the re-use of abandoned industrial areas. The LRT connects the neighbourhoods with the Lines 1 and 2, providing potential for new urban transport. The LRT will 5 stops: Tremelloni Anassagora, Tremelloni Gassmann, Tremelloni Tognazzi, Adriano Tremelloni, Adriano Mastroianni. The LRT will an interchange with the Line 2 at Cascina Gobba.